Fiber Cuts affecting Customers connected in CtrlS Mumbai Hyperscale DC1, NTT NAV01 Mahape and Nxtra Mahape
Major incident
Mumbai
Mumbai Peering
Mumbai Network
2026-07-14 19:09 IST
· 36 minutes
Updates
Issue
July 14, 2026 · 19:42 IST
We have noted a significant decrease in network activity within the Extreme IX infrastructure, primarily attributed to the occurrence of multiple fiber cuts in both our primary and backup links.
This unfortunate event has resulted in an adverse impact on all affiliated members and content providers physically connected within Data Centers CtrlS Mumbai Hyperscale DC1, NTT NAV01 Mahape and Nxtra Mahape.
We sincerely apologise for any inconvenience caused by this disruption, and our technical teams are actively working to resolve the fiber cuts and restore normal operations as swiftly as possible.