Fiber Cuts affecting Customers connected in Yotta DC Mumabi along with some Content Providers

Major incident Mumbai Mumbai Peering Mumbai Network
2025-11-04 21:19 IST · 20 minutes

Updates

Resolved

Our backup fiber path has been successfully restored, and all sessions within Yotta DC are now operational. Network activity has returned to normal levels, and traffic is flowing through stable routes.

We continue to monitor the network closely to ensure full stability while restoration work on the primary path progresses.

November 4, 2025 · 21:38 IST
Issue

We have noted a significant decrease in network activity within the Extreme IX infrastructure, primarily attributed to the occurrence of multiple fiber cuts in both our primary and backup links.

This unfortunate event has resulted in an adverse impact on all affiliated members and content providers physically connected within Data Centers Yotta DC.

We sincerely apologies for any inconvenience caused by this disruption, and our technical teams are actively working to resolve the fiber cuts and restore normal operations as swiftly as possible.

November 4, 2025 · 21:19 IST