Fiber Cuts affecting Customers in Bangalore
Major incident
Bangalore
Bangalore Peering
Bangalore Network
2024-07-06 14:15 IST
· 2 hours, 44 minutes
Updates
Update
July 6, 2024 · 16:33 IST
Based on the latest information provided by the vendor, the estimated resolution time is 45 minutes. we will continue to provide you with updates as they become available.
Issue
July 6, 2024 · 14:15 IST
We regret to inform you that multiple fiber cuts have occurred, causing the isolation of Micronova, Netmagic, Nxtra, CtrlS, and Sify data centers. Our vendor is actively working to resolve the issue and restore connectivity as swiftly as possible.